Project Name: Various Small Works
Client: Southern Gas Networks
Location: Hampshire and Dorset
Duration: Aug 06 ongoing
Since introducing Forest to Southern Gas Networks (SGN) based
in Poole, Dorset in August 2006 we have become their primary supplier
of traffic management services for schemes ranging from small
local road closures to high profile City Centre schemes to facilitate
their gas main replacement work. Key elements to our successful
partnership are:
-
Working closely with SGN through regular site and management
visits Forest have been able to build up a strong working
relationship, understanding the client needs and nature of
their business. We have been able to offer expert advise to
ensure that traffic management is compliant with legislation,
advising on aspects such as minimum lane widths, temporary
traffic management layouts, use of correct equipment and utilisation
of signs.
-
Early involvement in schemes has allowed us to provide exact
solutions for traffic management to meet the needs of SGN,
providing maximum working space and safety, whilst satisfying
the requirements of the local authority and minimising the
impact on the public
-
Because of our strong relationships with Local Authorities,
Forest have been able to liaise direct with them to ensure
full approval of traffic management layout’s, often
at short notice and with many special signs and requirements;
this has allowed SGN to focus on their activities in the knowledge
that the traffic management is taken care of.
-
During recent City Centre schemes in Southampton and Lymington,
Forest have been able to provide increased safety to the public
by suggesting alternative products and manufacturing numerous
special signs. In Southampton this enabled us to clearly separate
the public from the SGN works using red and white water filled
delineation barrier with anti-climb fencing behind it as an
alternative to cones and low level barrier which was prone
to abuse by the public. On both of these schemes and many
others using our local knowledge of the road network and landmarks
we have manufactured and installed special signs clearly indicting
traffic routes and pedestrian routes
-
Because of our 24/7 call facility SGN have been able to
utilise our services for both planned and emergency works.
In emergency situations, or where traffic management is required
on site at short notice, we have been able to respond within
2 hours. In many cases operatives have been despatched instantly
and we have been on site within the hour to install equipment
allowing SGN to undertake their work.
-
On all schemes we have been able to provide CAD drawings,
often at very short notice, both at the beginning and through-out.
This has been particularly useful where unknown elements such
as unplanned excavations are required and subsequently a new
traffic management solution to the one originally intended
is required. By producing and submitting these CAD drawings
to the local authority, sometimes within hours of the requirement
being identified, has allowed SGN work to progress with minimal
delay because all parties are clear to the traffic management
layout proposals. This is backed up by on site meetings with
all parties both prior to and throughout schemes to identify
and provide solutions to potential issues.
|